Supporting a leading UK steelwork company.

Service Project Controls
Year 2020 - 2022

Client

Project

Victoria & Albert Museum

Green Park Station

Overview

Baseone helped one of the UK’s leading steelwork companies plan and schedule the design, manufacture, and installation of structural steel.

The Customer

The Bourne Group is a privately owned and managed business specialising in structural steelwork, car park design, structural innovation, and technical solutions.

Bourne Group has grown to 120 plus employees that work a wide range of market sectors. They have covered airports, commercial new build, refurbishment, infrastructure, energy, and waste.

rsz 1400reading stan mg 5623 edit

 

The Challenge

Bourne were delivering steel EPC contracts in the UK, including at the V&A and Green Park Station.

Bourne steel needed full project visibility of scope and resource from design to install of steel works. Primavera schedules were required as part of contractual obligation which also determined the quality requirements the scheduling.

Bourne needed to track actual events, and report the project to allow understanding of resources, time and changes to scope.

baseone v-a-museum
baseone v-a-museum-6
baseone v-a-museum-3
baseone v-a-museum-5
baseone rsz_1400-2_guys_side_track_green_park

 

Our Solution

Working with Bourne managers and engineers, Baseone created project schedules from scope documentation.

Using Oracle Primavera P6 we planned project activity, resources, roles, and cost. We developed the Work Breakdown Structure (WBS), tracked key milestones and events, and produced the initial baseline schedule.

From project start date we worked with Bourne to regularly update the schedules, and keep track of time spent, and work performed by the site teams.

We tracked key client interfaces and identified any out of scope work that was requested or performed. Any extra work could be claimed back from the client.

We also generated all project related reports and consulted with Bourne’s clients (Balfour Beatty) to explain the scheduling work where required.

 

The Results

The projects we worked on for Bourne Group were a success. Although there were delays in the schedule, they identified as caused by other parties, or were due to out-of-scope work.

On one project, 10k hours were successfully claimed as out of scope and reimbursed to Bourne Group, which led to an increased pay out of 22%.

Bourne Group also saved around £44k from working with BaseOne, as opposed to hiring an internal Project Controls team.

Key Value Metrics
Result Value
Out-of-scope work identified 10,000 hrs
Revenue increase from Baseline 22%

 